Completion rate of the third German call for tenders: 90%.

In Germany, the completion rate for projects accepted in the third tender of December 2015, with construction scheduled for completion on 18 December 2017, is 90%. This

3rd call for tenders had selected 43 projects for a cumulative capacity of 204 MW, at a price of 0.08 €/kWh. The projects ranged in size from 0.75 MW to 10 MW.

This project completion rate of 90% is comparable to the 96% of the first call for tenders, and identical to that of the second round.

PV Magazine of 9 January 2018