L R AS Published on Sunday 28 August 2016 - n° 157 - Categories:minister-regulation

Purchase price for the 3rd quarter 2016

Feed-in tariffs for the third quarter of 2016
The Energy Regulatory Commission (CRE) published its connection reports on 25 July:
- Applications for the connection of building-integrated facilities ? 9 kWp, reached 20 MWp (compared with 23.4 MWp for the same period in 2015, and down 16% compared with the first quarter of 2016, 24 MWp), which implies a 1.5% reduction in the corresponding feed-in tariff.

- requests for connection of simplified building-integrated installations with a capacity of ? 100 kWp reached 89 MWp (an increase of more than 3.3 times the volume for the same period in 2015, and a 3.48% increase over the previous quarter, 86 MWp), which implies a 4% reduction in the corresponding feed-in tariff.
- Hence the following tariff

Type of installationPowerfrom 01/07/16 to 30/09/16
Integrated into the building0-9kW] [0-9kW]24.29 c€/kWh
Simplified integration into the building]0-36 kW]12.72 c€/kWh
]36-100 kW]12.13 c€/kWh
Without integration, or outside the above criteria, or on the ground0-12MW] [0-12MW]5.65 c€/kWh

Enerplan of July 26th